Regional Wastewater Disposal Tulkarem

Name of Employer:
Wadi Zumeir Joint Service Council For Wastewater Project – Tulkarem / Kfw
Duration:
66 months
Date of Completion:
February, 2018
Location:
Tulkarem , Palestine
Sector:
Electromechanical Works, Water and Wastewater Networks, Infrastructure

Brief Description of the Works performed:

  • Construction of 15,000 LM UPVC Pipeline of Dia. 150 – 300 mm and 800 LM Concrete Pipeline of Dia. 600 mm with house connections
  • Construction of 10200 LM of concrete pipeline of Dia. 500mm, 600mm, 700mm & 1000mm.
  • Construction of 10700 LM corrugated pipelines of Dia. 160mm, 250mm, 300mm & 400mm.
  • Construction of two pumping stations.